question
Which of the following is NOT part of project​ controlling?
answer
sequencing and allotting time to all project activities
question
The three phases involved in the management of large projects are
answer
​planning, scheduling, and controlling.
question
The project organization may be LESS helpful when
answer
the job is familiar to the existing organization.
question
What is the shortest duration required to complete an​ activity?
answer
crash time
question
Which of the following is a limitation of PERT and​ CPM?
answer
There is the inherent danger of placing too much emphasis on the critical path.
question
Which of these statements is NOT true about project​ scheduling?
answer
Project scheduling helps make better use of resources by identifying the​ non-critical paths through the network.
question
Which of these time estimates is NOT used in​ PERT?
answer
standard time
question
What is the most popular example of specialized software for managing​ projects?
answer
Microsoft Project
question
How is the EF​ computed?
answer
ES​ + Activity time
question
Gantt charts are
answer
planning charts used to schedule resources and allocate time.
question
Which of the following is an advantage of PERT and​ CPM?
answer
Straightforward concept and not mathematically complex.
question
Which of the following is NOT true about Gantt​ charts?
answer
Gantt charts adequately illustrate the interrelationships between the activities and the resources.
question
Which column in Microsoft Project defines the precedence relationships among the​ activities?
answer
predecessors
question
Which of the following is NOT a technique that allows managers to​ plan, schedule, and control​ projects?
answer
​Factor-rating method
question
The most realistic estimate of the time required to complete an activity is referred to as​ what?
answer
most likely time
question
Computerized​ PERT/CPM reports and charts do NOT include
answer
probability estimates for​ on-time completion.
question
Which of the following is a direct responsibility of the project​ manager?
answer
making sure that the people assigned to the project receive the​ motivation, direction, and information needed to do their jobs
question
Which of the following activities are NOT part of project​ scheduling?
answer
Make sure all necessary activities are finished in proper sequence and on time.
question
The latest finish of an activity is
answer
​Min{LS of all immediate following​ activities}.
question
Which of the following is used for computations in​ CPM?
answer
normal time