question
Which of the following is NOT part of project‚Äč controlling?
answer
sequencing and allotting time to all project activities
question
The three phases involved in the management of large projects are
answer
‚Äčplanning, scheduling, and controlling.
question
The project organization may be LESS helpful when
answer
the job is familiar to the existing organization.
question
What is the shortest duration required to complete an‚Äč activity?
answer
crash time
question
Which of the following is a limitation of PERT and‚Äč CPM?
answer
There is the inherent danger of placing too much emphasis on the critical path.
question
Which of these statements is NOT true about project‚Äč scheduling?
answer
Project scheduling helps make better use of resources by identifying the‚Äč non-critical paths through the network.
question
Which of these time estimates is NOT used in‚Äč PERT?
answer
standard time
question
What is the most popular example of specialized software for managing‚Äč projects?
answer
Microsoft Project
question
How is the EF‚Äč computed?
answer
ES‚Äč + Activity time
question
Gantt charts are
answer
planning charts used to schedule resources and allocate time.
question
Which of the following is an advantage of PERT and‚Äč CPM?
answer
Straightforward concept and not mathematically complex.
question
Which of the following is NOT true about Gantt‚Äč charts?
answer
Gantt charts adequately illustrate the interrelationships between the activities and the resources.
question
Which column in Microsoft Project defines the precedence relationships among the‚Äč activities?
answer
predecessors
question
Which of the following is NOT a technique that allows managers to‚Äč plan, schedule, and control‚Äč projects?
answer
‚ÄčFactor-rating method
question
The most realistic estimate of the time required to complete an activity is referred to as‚Äč what?
answer
most likely time
question
Computerized‚Äč PERT/CPM reports and charts do NOT include
answer
probability estimates for‚Äč on-time completion.
question
Which of the following is a direct responsibility of the project‚Äč manager?
answer
making sure that the people assigned to the project receive the‚Äč motivation, direction, and information needed to do their jobs
question
Which of the following activities are NOT part of project‚Äč scheduling?
answer
Make sure all necessary activities are finished in proper sequence and on time.
question
The latest finish of an activity is
answer
‚ÄčMin{LS of all immediate following‚Äč activities}.
question
Which of the following is used for computations in‚Äč CPM?
answer
normal time