question
For a project manager, monitoring and controlling _____.
answer
requires guiding, supervising, and coordinating the project team's workload
question
A project manager must balance ____ to achieve a workable schedule; graphical planning aids like the one in the accompanying figure can help in the process.
answer
all of the above
question
The accompanying figure shows task ____, which each might represent several activities that can be shown in a more detailed chart.
answer
groups
question
Gantt charts often are included in progress reports to show project status graphically.
answer
False
question
A proxy system is a small system that is developed as a basis for understanding a new environment.
answer
False
question
A ____ is an event that could affect a project negatively.
answer
risk
question
Quantitative risk analysis evaluates each risk by estimating the probability that it will occur and the degree of impact.
answer
False
question
A ____ might involve maximums for one or more resources.
answer
constraint
question
A _____ cannot be started until one or more other tasks are completed.
answer
dependent task
question
A ____ path includes all tasks that are vital to the project schedule.
answer
critical
question
A project manager's planning _____.
answer
includes identifying project tasks and estimating completion times and costs
question
A project manager's scheduling function _____.
answer
involves staffing, which includes selecting the project team and assigning specific tasks to team members
question
A project manager, or project leader, usually is a senior systems analyst or an IT department manager if the project is large.
answer
True
question
A project schedule exists independent of the underlying task pattern.
answer
False
question
A risk ____ plan is a proactive effort to anticipate a risk and describe an action plan to deal with it.
answer
response
question
A risk management plan includes a review of all of the following EXCEPT ____.
answer
employees
question
A significant disadvantage of integrated project management software is that it prevents the project manager from adjusting schedules, estimates, or resource assignments rapidly enough to develop a workable plan.
answer
False
question
A task is any work that requires the use of company resources including all of the following EXCEPT ____.
answer
controlling capital
question
A(n) ____ chart can be used to display the qualitative risk analysis matrix.
answer
XY
question
A(n) ____ chart displays complex task patterns and relationships.
answer
PERT/CPM
question
All of the following affect project time requirements EXCEPT ____.
answer
work breakdown structure
question
All of the following are claims that Microsoft makes about the risk management capabilities of Microsoft Project 2007 EXCEPT ____.
answer
the linking of risks with specific vendors
question
All of the following are metrics of a successful project EXCEPT ____.
answer
completion with the same personnel as were on the team at the outset
question
All of the following are possible causes of cost overruns related to human resource factors EXCEPT ____.
answer
inaccurate TCO forecast
question
All of the following are versions of Microsoft Office Project 2007 EXCEPT ____.
answer
Enterprise
question
Although a Gantt chart provides more detailed information about a project, a PERT/CPM chart offers a rapid overview that graphically displays the timing, duration, and progress of each task.
answer
False
question
For a project manager, monitoring and controlling _____.
answer
includes monitoring the progress of the project, evaluating results, and taking corrective action when necessary to stay on target
question
Gantt charts are an ideal tool for controlling a complex project because they provide plenty of detailed information.
answer
False
question
Generally, systems analysts review the work of other systems analysts, and programmers review the work of other programmers, as a form of peer review, in structured walk-throughs.
answer
True
question
If any task along the critical path falls behind schedule, the entire project is delayed.
answer
True
question
If it will take one person 20 days to perform a particular task, it is true that two people could complete the same task in 10 days or that 10 people could perform the task in two days.
answer
False
question
In Open Workbench, unlike in Microsoft Project, you create tasks and durations, indicate dependencies, and assign resources.
answer
False
question
In a PERT/CPM chart, each rectangular box, called a task box, has five sections that contain important information about a task.
answer
True
question
In a PERT/CPM chart, each task has all of the following EXCEPT a(n) ____.
answer
reference to successor tasks
question
In addition to tasks, every project has ____, which are reference points used to monitor progress and manage the project.
answer
milestones
question
In any project, large or small, tasks depend on each other and must be performed in a sequence.
answer
True
question
In developing time and cost estimates, project managers must consider _____.
answer
all of the above
question
In most systems analysis tasks, time and people are interchangeable.
answer
False
question
Many project managers find ____ charts more helpful for scheduling, monitoring, and controlling projects.
answer
PERT/CPM
question
Microsoft's risk management model includes all of the following EXCEPT ____.
answer
probability, which indicates the degree of adverse effect should the risk occur, on a scale of 1 to 10
question
Most managers recognize that problems do occur on most projects; it is better to alert management sooner rather than later.
answer
True
question
Most project managers find that Gantt charts are better tools for managing large projects.
answer
False
question
Most risk identifications include a brief description of all of the following EXCEPT ____.
answer
the team member most vulnerable to a given risk
question
Often, two or more concurrent tasks depend on a single prior task, which is called a successor task.
answer
False
question
Open Workbench can exchange files with Microsoft Project by importing and exporting the data in ____ file format.
answer
XML
question
PERT/CPM and Gantt charts are mutually exclusive techniques.
answer
False
question
PERT/CPM is called a(n) ____ technique, because it analyzes a large, complex project as a series of individual tasks.
answer
bottom-up
question
Problems with timetables and project milestones can indicate ____.
answer
any of the above
question
Project managers always must be aware of the ____ path, so they can monitor the vital tasks and keep the project on track.
answer
critical
question
Project planning is a dynamic task and involves constant change.
answer
True
question
Project scheduling involves all of the following EXCEPT ____.
answer
defining project constraints
question
Project status meetings give project managers an opportunity to seek input and conduct brainstorming sessions.
answer
True
question
Project status meetings give project managers an opportunity to seek input and conduct brainstorming sessions.
answer
True
question
Tasks that are not on the critical path cannot be ignored.
answer
True
question
The capabilities of project team members do not affect time requirements.
answer
False
question
The first step in creating a WBS is to ____.
answer
identify all tasks
question
The first step in the creation of a PERT/CPM chart is to ____.
answer
identify all the project tasks
question
Two or more concurrent tasks often depend on a single prior task, which is called a(n) ____ task.
answer
predecessor
question
The purpose of quantitative risk analysis is to understand the actual impact in terms of dollars, time, project scope, or quality.
answer
True
question
Using a WBS allows you to manage a project as one large task.
answer
False
question
Using prior experience to make time and cost estimates works best for large projects.
answer
False
question
When an information system does not meet business requirements, causes might include ____.
answer
any of the above
question
When maintaining schedules, if enough ____ and frequent checkpoints exist, problems will be detected rapidly.
answer
milestones
question
When several tasks can start at the same time, each is called a ____ task.
answer
concurrent
question
When several tasks can take place at the same time, each is called a sequential task.
answer
False
question
When tasks must be completed one after another, they are called concurrent tasks.
answer
False
question
When two or more concurrent tasks depend on a single prior task, each of the concurrent tasks is called a predecessor task.
answer
False
question
When two or more concurrent tasks depend on a single prior task, the concurrent tasks are called ____ tasks.
answer
successor
question
Which of the following versions of Microsoft Project includes support for large, enterprise-wide projects?
answer
Server
question
____ is open-source software that is supported by a large group of users and developers.
answer
Open Workbench