PM CHAPTER 6

3 September 2022
4.7 (114 reviews)
95 test answers

Unlock all answers in this set

Unlock answers (91)
question
1. An activity is an element of work that has an expected duration, cost, and resource requirements.
answer
TRUE An activity or task is an element of work normally found on the work breakdown structure (WBS) that has expected duration, cost, and resource requirements.
question
2. In project time management, the primary output of defining activities is a schedule management plan
answer
FALSE In project time management, the main output of defining activities are an activity list, activity attributes, a milestone list, and project management plan updates.
question
3. In project time management, the next step after sequencing activities is to define these activities.
answer
FALSE Estimating activity resources involves estimating how many resources— people, equipment, and materials—a project team should use to perform project activities. In project time management, this process follows after sequencing activities.
question
4. Project schedules grow out of basic documents such as the project charter.
answer
TRUE Project schedules grow out of the basic documents that initiate a project. The project charter often mentions planned project start and end dates, which serve as the starting points for a more detailed schedule.
question
5. A schedule management plan includes information which describes the format and frequency of schedule reports required for the project.
answer
TRUE A schedule management plan includes information on reporting formats. This information describes the format and frequency of schedule reports required for the project. In addition, it also includes information on process descriptions and describes how all of the schedule management processes will be performed.
question
6. To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes.
answer
TRUE Defining activities involves identifying the specific actions that will produce the project deliverables in enough detail to determine resource and schedule estimates. The project team reviews the schedule management plan, scope baseline, enterprise environmental factors, and organizational process assets to begin defining activities.
question
7. It is important for the activity list and activity attributes to be in agreement with the work breakdown structure.
answer
TRUE The activity list and activity attributes should be in agreement with the work breakdown structure. Information is added to the activity attributes as it becomes available; this information includes logical relationships and resource requirements that are determined in later processes.
question
8. Milestones are easy to achieve and are always achieved through one main activity.
answer
FALSE A milestone on a project is a significant event that normally has no duration. It often takes several activities and a lot of work to complete a milestone, but the milestone itself is like a marker to help in identifying necessary activities.
question
9. After defining project activities, the next step in project time management is developing the schedule.
answer
FALSE After defining project activities, the next step in project time management is sequencing them or determining their dependencies.
question
10. A dependency pertains to the sequencing of project activities or tasks.
answer
TRUE A dependency or relationship pertains to the sequencing of project activities or tasks. Determining these relationships or dependencies among activities has a significant impact on developing and managing a project schedule.
question
11. Network diagrams are the preferred technique for showing activity sequencing.
answer
TRUE Network diagrams are the preferred technique for showing activity sequencing. A network diagram is a schematic display of the logical relationships among project activities and their sequencing.
question
12. The arrows in a network diagram represent missed milestones in a project.
answer
FALSE A network diagram is a schematic display of the logical relationships among project activities and their sequencing. The arrows in a network diagram represent the activity sequencing or relationships between tasks.
question
13. In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.
answer
FALSE The network diagram represents activities that must be done to complete the project. Not every item on the WBS needs to be shown on the network diagram; only activities with dependencies need to be shown.
question
14. A merge occurs when one node precedes mutiple nodes.
answer
FALSE A merge occurs when two or more nodes precede a single node. On the other hand, bursts occur when two or more activities follow a single node.
question
15. Start-to-finish relationships are the most frequently used dependencies between activities.
answer
FALSE One of the four types of dependencies or relationships between activities is the start-to-finish dependency. This is a relationship in which the "from " activity must start before the "to" activity can be finished. This type of relationship is rarely used, but it is appropriate in some cases.
question
16. A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.
answer
FALSE The precedence diagramming method offers a number of advantages over the AOA technique. One advantage is that using this method avoids the need to use dummy activities.
question
17. In project time management, one should control the scheule before estimating the duration for each activity.
answer
FALSE In project time management, before one can estimate the duration for each activity, one must have a good idea of the quantity and type of resources (people, equipment, and materials) that will be assigned to each activity.
question
18. In a Gantt chart, thick black bars represent milestones achieved in a project.
answer
FALSE Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in calendar form. In a Gantt chart, a black diamond symbol represents a milestone.
question
19. A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates.
answer
TRUE A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates. It allows the project manager to monitor schedule progress on individual tasks and the whole project.
question
20. A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.
answer
FALSE The main advantage of using Gantt charts is that they provide a standard format for displaying planned and actual project schedule information.
question
21. In a critical path analysis, the shortest path is what drives the completion date for the project.
answer
FALSE In a critical path analysis, several tasks are done in parallel on projects, and most projects have multiple paths through a network diagram. The longest path or the path that contains the critical tasks is what drives the completion date for the project.
question
22. The critical path on a project can change as the project progresses.
answer
TRUE The critical path represents the shortest time required to complete a project. The critical path on a project can change as the project progresses.
question
23. A backward pass through the network diagram determines the early start and early finish dates for each activity.
answer
FALSE A backward pass through the network diagram determines the late start and late finish dates for each activity. In contrast, a forward pass determines the early start and early finish dates for each activity.
question
24. Knowing the amount of float allows project managers to know whether a project schedule is flexible.
answer
TRUE Knowing the amount of float or slack allows project managers to know whether the schedule is flexible and how flexible it might be. A fast and easy way to determine early and late start and finish dates and free and total slack amounts for activities is by using project management software.
question
25. The main disadvantage of crashing is that it lengthens the time needed to finish a project.
answer
FALSE The main advantage of crashing is that it shortens the time needed to finish a project. The main disadvantage is that it often increases total project costs.
question
26. The technique of fast tracking can result in lengthening the project schedule.
answer
TRUE The main disadvantage of fast tracking is that it can lengthen the project schedule because starting some tasks too soon often increases project risk and results in rework.
question
27. Critical chain scheduling assumes that resources multitask and maximizes multitasking.
answer
FALSE Critical chain scheduling is a method that considers limited resources when creating a project schedule and includes buffers to protect the project completion date. It assumes that resources do not multitask or at least minimize multitasking.
question
28. One of PERT's main disadvantages is that it does not address the risk associated with duration estimates.
answer
FALSE PERT's main disadvantages are that it involves more work than CPM because it requires several duration estimates, and there are better probabilistic methods for assessing schedule risk.
question
29. The final process in project time management is developing the schedule.
answer
FALSE The final process in project time management is controlling the schedule Like scope control, schedule control is a portion of the integrated change control process under project integration management.
question
30. A drawback of the project management software is that it does not have the capacity to calculate the critical path(s) for a project.
answer
FALSE A project management software can be used to draw network diagrams, determine the critical path for a project, create Gantt charts, and report, view, and filter specific project time management information
question
1. The first process involved in project time management is _____ . a. defining activities b. estimating activity durations c. planning schedule management d. sequencing activities
answer
C Schedule management is the first process in project time management and involves determining the policies, procedures, and documentation that will be used for planning, executing, and controlling the project schedule.
question
2. Which of the following processes in project time management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables? a. Defining activities b. Sequencing activities c. Developing the schedule d. Estimating activity durations
answer
A In project time management, the process of defining activities involves identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables.
question
3. In project time management, which of the following processes generate the main outputs of an activity list, activity attributes, and a milestone list? a. Sequencing activities b. Defining activities c. Resource estimating activities d. Estimating activity durations
answer
B In project time management, the main outputs of the sequencing activities process are an activity list, activity attributes, a milestone list, and project management plan updates.
question
4. In project time management, which of the following processes primarily involve identifying and documenting the relationships between project activities? a. Defining activities b. Sequencing activities c. Planning schedule management d. Estimating activity durations
answer
B Sequencing activities involves identifying and documenting the relationships between project activities. The main outputs of this process include project schedule network diagrams and project documents updates.
question
5. In project time management, which of the following processes involve calculating the number of work periods that are needed to complete individual activities? a. Defining activities b. Sequencing activities c. Planning schedule management d. Estimating activity durations
answer
D Estimating activity durations involves estimating the number of work periods that are needed to complete individual activities. Outputs include activity duration estimates and project documents updates.
question
6. In project time management, which of the following processes involve analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule? a. Planning schedule management b. Developing the schedule c. Controlling the schedule d. Defining activities
answer
B Developing the schedule involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule. Outputs include a schedule baseline, project schedule, schedule data, project calendars, project management plan updates, and project documents updates.
question
7. In project time management, the process of_____ primarily involves checking and managing changes to the project schedule. a. estimating activity durations b. developing the schedule c. controlling the schedule d. estimating activity resources
answer
C In project time management, the process of controlling the schedule involves controlling and managing changes to the project schedule. Outputs include work performance information, schedule forecasts, and change requests among others.
question
8. In project time management, a(n) _____ is an output of controlling the schedule a. activity duration estimate b. project management plan update c. activity attribute d. milestones list
answer
B Controlling the schedule involves controlling and managing changes to the project schedule. Outputs include work performance information, schedule forecasts, change requests, project management plan updates, project documents updates, and organizational process assets updates.
question
9. Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule? a. Resource breakdown structure b. Milestones list c. Organizational process assets update d. Project charter
answer
D The project charter often mentions planned project start and end dates, which serve as the starting points for a more detailed schedule.
question
10. Which of the following is a difference between an activity list and an activity attribute? a. As opposed to an activity attribute, an activity list provides resource requirements and constraints related to activities b. An activity list provides a more concrete list of milestones for a project than an activity attribute. c. An activity attribute is a tabulation of activities to be included on a project schedule whereas an activity list is not.. d. An activity attribute provides more schedule-related information about each activity than an activity list.
answer
D The activity list is a tabulation of activities to be included on a project schedule. The list should include the activity name, an activity identifier or number, and a brief description of the activity. The activity attributes provide more schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, and so forth.
question
11. A(n) _____ on a project is a significant event that normally has no duration. a. milestone b. activity attribute c. activity sequence d. schedule baseline
answer
A A milestone on a project is a significant event that normally has no duration. It often takes several activities and a lot of work to complete a milestone, but the milestone itself is like a marker to help in identifying necessary activities.
question
12. In project time management, the main goal of _____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work. a. defining activities b. estimating activity durations c. estimating activity resources d. controlling the schedule
answer
A The goal of defining activities is to ensure that the project team completely understands all the work it must do as part of the project scope so the team can start scheduling the work. Activity information is a required input to the other time management processes.
question
13. In project time management, the next step after defining project activities is: a. planning schedule management. b. determining their dependencies. c. controlling the schedule. d. estimating activity duration.
answer
B After defining project activities, the next step in project time management is sequencing them or determining their dependencies. The sequencing process involves evaluating the reasons for dependencies and the different types of dependencies.
question
14. Which of the following types of dependencies are inherent in the nature of work being performed on a project? a. Mandatory b. Discretionary c. External d. Random
answer
A Mandatory dependencies are inherent in the nature of work being performed on a project. They are sometimes referred to as hard logic.
question
15. _____ dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options. a. Mandatory b. Discretionary c. External d. Inherent
answer
B Discretionary dependencies are defined by the project team. They are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.
question
16. Which of the following dependencies involve relationships between project and non-project activities? a. Mandatory b. Discretionary c. External d. Inherent
answer
C External dependencies involve relationships between project and non-project activities.
question
17. In an AOA network diagram, _____ occur when two or more activities follow a single node. a. combinations b. buffers c. mergers d. bursts
answer
D When creating an AOA network diagram, bursts occur when two or more activities follow a single node.
question
18. A network diagramming technique in which boxes represent activities is known as a(n) _____. a. PDM b. CPM c. ADM d. PERT
answer
A The precedence diagramming method (PDM) is a network diagramming technique in which boxes represent activities. It is particularly useful for visualizing certain types of time relationships.
question
19. AOA network diagrams use only _____ dependencies. a. start-to-start b. finish-to-start c. finish-to-finish d. start-to-finish
answer
B A finish-to-start dependency is the most common type of relationship or dependency and AOA network diagrams use only finish-to-start dependencies. It is a relationship in which the "from" activity or predecessor must finish before the "to" activity or successor can start.
question
20. Which of the following is a relationship in which the "from" activity cannot start until the "to" activity is started? a. Start-to-start b. Finish-to-finish c. Finish-to-start d. Start-to-finish
answer
A A start-to-start dependency is a relationship in which the "from" activity cannot start until the "to" activity or successor is started.
question
21. Which of the following is true of a finsih-to-finish dependency? a. It is a dependency in which the "from" activity cannot start until the "to" activity or successor is started. b. It is a dependency in which in which the "from" activity must finish before the "to" activity or successor can start. c. It is a dependency in which the "from" activity must be finished before the "to" activity can be finished. d. It is a dependency in which the "from" activity must start before the "to" activity can be finished.
answer
C A finish-to-finish dependency is a relationship in which the "from" activity must be finished before the "to" activity can be finished. One task cannot finish before another finishes.
question
22. Which of the following is true of dummy activities? a. They have long durations. b. They show logical relationships between activities. c. They have a large range of resources. d. They have limited time periods.
answer
B Dummy activities have no duration and no resources, but are occasionally needed on AOA network diagrams to show logical relationships between activities.
question
23. Which of the following is one of the main outputs of estimating activity resources process? a. Project documents update b. Milestone list c. Work breakdown structure d. Activity duration estimate
answer
A The main outputs of the resource estimating process include a list of activity resource requirements, a resource breakdown structure, and project documents updates.
question
24. After working with key stakeholders to define activities and calculate their resources, the next process in project time management is to: a. develop the schedule. b. control the schedule. c. determine their dependencies. d. estimate the duration of activities.
answer
D After working with key stakeholders to define activities, determine their dependencies, and estimate their resources, the next process in project time management is to estimate the duration of activities.
question
25. In project time management, the ultimate goal of _____ is to provide a basis for monitoring project progress for the time dimension of the project. a. defining activities b. sequencing activities c. developing a schedule d. estimating activity resources
answer
C The ultimate goal of developing a realistic project schedule is to provide a basis for monitoring project progress for the time dimension of the project. Project time management processes often go through several iterations before a project schedule is finalized.
question
26. _____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format. a. Gantt charts b. Critical path analysis c. Arrow diagramming method d. PERT analysis
answer
A Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in calendar form. They are sometimes referred to as bar charts because the activities' start and end dates are shown as horizontal bars.
question
27. Which of the following is a network diagramming technique used primarily to predict total project duration? a. Gantt chart b. Critical path analysis c. Resource breakdown structure d. Arrow diagramming method
answer
B Critical path method (CPM) —also called critical path analysis —is a network diagramming technique used to predict total project duration. This important tool helps combat project schedule overruns.
question
28. The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float. a. longest; longest b. longest; shortest c. shortest; longest d. shortest; shortest
answer
B A critical path for a project is the series of activities that determine the earliest time by which the project can be completed. It is the longest path through the network diagram and has the least amount of slack or float.
question
29. The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____. a. forward pass b. backward pass c. fast tracking d. free slack
answer
D A technique that can help project managers make schedule trade-offs is determining the free slack and total slack for each project activity. Free slack or free float is the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.
question
30. _____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date. a. Total slack b. Free float c. Backward pass d. Forward pass
answer
A Total slack or total float is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.
question
31. The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date. a. early finish date b. late finish date c. late start date d. early start date
answer
C The late start date is the latest possible time an activity might begin without delaying the project finish date.
question
32. The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____. a. dependency b. crashing c. critical chain scheduling d. feeding buffers
answer
B Crashing is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost. The main advantage of crashing is shortening the time needed to finish a project.
question
33. Which of the following techniques involve doing activities in parallel that one would normally do in sequence? a. Critical chain scheduling b. Crashing c. Fast tracking d. PERT analysis
answer
C Fast tracking involves doing activities in parallel that one would normally do in sequence. The main advantage of fast tracking is that it can shorten the time needed to finish a project.
question
34. A similarity between the crashing technique and the fast tracking technique is that: a. both spread out tasks over a long period of time to ensure the quality of work is maintained. b. both invariably result in increases in total project costs. c. both can shorten the time needed to finish a project. d. both are network diagramming techniques used primarily to predict total project duration.
answer
C The main advantage of fast tracking, like crashing, is that it can shorten the time needed to finish a project.
question
35. Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks. a. critical paths b. feeding buffers c. dummy activities d. fast tracking
answer
B Critical chain scheduling protects tasks on the critical chain from being delayed by using feeding buffers, which consist of time added before tasks on the critical chain if they are preceded by other tasks that are not on the critical path.
question
36. _____ states that work expands to fill the time allowed. a. Murphy's Law b. Miller's Law c. Parkinson's Law d. Einstein's Law
answer
C Parkinson's Law states that work expands to fill the time allowed.
question
37. A difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) is that: a. CPM addresses the risk associated with duration estimates whereas PERT does not. b. unlike CPM, PERT estimates only when there is no risk of uncertainty. c. CPM involves more work than PERT because it requires several duration estimates. d. PERT uses different duration estimates whereas CPM uses one specific duration estimate.
answer
D PERT uses probabilistic time estimates —duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations —instead of one specific or discrete duration estimate, as CPM does.
question
38. Which of the following is a silimarity between scope control and schedule control? a. Both are initial processes of project time management. b. Both of their primary goals is to define project goals and milestones. c. Both are portions of the integrated change control process under project integration management. d. Both of these processes should occur before estimating activity durations.
answer
C Like scope control, schedule control is a portion of the integrated change control process under project integration management. Controlling the schedule is the final process in project time management.
question
39. Which of the following is an output of schedule control? a. Lessons-learned reports b. Activity attributes c. Resource requirements d. Milestones list
answer
A The main outputs of schedule control include work performance measurements, organizational process assets updates such as lessons-learned reports related to schedule control, change requests, project management plan updates, and project documents updates.
question
40. A draft schedule for a project is most likely to be found in a _____. a. project buffer b. project charter c. resource breakdown structure d. project's dummy activities list
answer
B One of the first reality checks for a project manager is to review the draft schedule that is usually included in the project charter. Although this draft schedule might include only a project start and end date, the project charter sets some initial schedule expectations for the project.
question
1. In a project schedule, the variable that has the least amount of flexibility is _____.
answer
time
question
2. _____ involves the processes required to ensure timely completion of a project.
answer
Project time management
question
3. In project time management, the process of _____ involves deciding how many people, equipment, and materials a project team should use to perform project activities.
answer
estimating activity resources
question
4. After reviewing the project management plan, project charter, enterprise environmental factors, and organizational process assets, the project team uses expert judgment, analytical techniques, and meetings to develop the _____.
answer
schedule management plan
question
5. The _____ is a tabulation of activities to be included on a project schedule.
answer
activity list
question
6. The activity list should include the _____, an activity identifier, and a brief description of the activity.
answer
activity name
question
7. In the activity defining process, the project team should review the _____ and activity attributes with project stakeholders before moving on to the next step in project time management.
answer
activity list
question
8. A(n) _____ is a schematic display of the logical relationships among project activities and their sequencing.
answer
network diagram
question
9. In a network diagram, a(n) _____ is the starting and ending point of an activity.
answer
node
question
10. In a(n) _____ relationship, the "from" activity must start before the "to" activity can be finished.
answer
start-to-finish
question
11. _____ have no duration and no resources but are occasionally needed on AOA network diagrams to show logical relationships between activities.
answer
Dummy activities
question
12. A hierarchical structure that identifies the project's resources by category and type is known as a(n) _____.
answer
resource breakdown structure
question
13. _____ is the number of workdays or work hours required to complete a task.
answer
Effort
question
14. Duration estimates can be provided as a discrete number, a range, or as a(n) _____.
answer
three-point estimate
question
15. The ultimate goal of developing a realistic project schedule is to provide a basis for monitoring project progress for the _____ dimension of the project.
answer
time
question
16. A(n) _____ Gantt chart compares planned and actual project schedule information.
answer
Tracking
question
17. A white diamond on a Tracking Gantt chart represents a(n) _____.
answer
slipped milestone
question
18. A(n) _____ for a project is the series of activities that determine the earliest time by which the project can be completed.
answer
critical path
question
19. A(n) _____ determines the early start and early finish dates for each activity in a project.
answer
forward pass
question
20. The _____ is based on the fact that any complex system at any point in time often has only one aspect or constraint that limits its ability to achieve more of its goal.
answer
Theory of Constraints (TOC)
question
21. _____ occurs when a resource works on more than one task at a time.
answer
Multitasking
question
22. _____ states that if something can go wrong, it will.
answer
Murphy's Law
question
23. The main outputs of _____ include work performance measurements, organizational process assets updates, and project document updates.
answer
schedule control
question
24. One of the first reality checks on scheduling that a project manager should make is to review the _____.
answer
draft schedule
question
25. A drawback of using _____ or sample files is that managers and their teams might rely heavily on them and ignore unique concerns for their particular projects.
answer
templates