question
A network has been crashed to the point where all activities are critical. Additional​ crashing:
answer
may require crashing multiple tasks simultaneously
question
Which of the following statements regarding CPM networks is​ true?
answer
if a specific project has multiple critical​ paths, all of them will have the same duration
question
Which of the following statements concerning CPM activities is​ false?
answer
The late finish of an activity is the earliest late start of all preceding activities.
question
What are the phases of project​ management?
answer
planning, scheduling, controlling
question
A simple CPM network has five​ activities, A,​ B, C,​ D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Which of the following statements is​ true?
answer
There are four paths in this network
question
Which of the following is the THIRD level in work breakdown structure​ (WBS)?
answer
subtasks in major tasks
question
Gantt charts are
answer
planning charts used to schedule resources and allocate time
question
The main difference between PERT and CPM is​ that:
answer
PERT employs 3 time estimates for each activity
question
A simple CPM network has three​ activities, D,​ E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=​4, E=​3, F=8.
answer
Critical Path = D-E-F duration 15
question
Which of the following is NOT true about Gantt​ charts?
answer
Gantt charts adequately illustrate the interrelationships between the activities and the resources
question
What is true about Gantt​ charts?
answer
1. Gantt charts are​ low-cost means of helping managers make sure that activities are planned. 2. Gantt charts are planning charts used to schedule resources and allocate time. 3. Gantt charts also can be used for scheduling repetitive operations.
question
Which of the following statements regarding​ time-cost tradeoffs in CPM networks is​ false?
answer
Crashing sometimes has the reverse result of lengthening the project duration.
question
Which of the following statements regarding CPM is​ true?
answer
All activities on the critical path have their LS equal to the maximum EF of all immediate predecessors.
question
Which of the following statements regarding critical paths is​ true?
answer
On a specific​ project, there can be multiple critical​ paths, all with exactly the same duration.