Project Cost Management - Ch 7 (True/False)

5 October 2022
4.7 (114 reviews)
30 test answers

Unlock all answers in this set

Unlock answers (26)
question
Overrun is the additional percentage amount by which estimates exceed actual costs.
answer
False
question
The primary output of the planning cost management process is a change request.
answer
False
question
IT project managers must be able to present and discuss project information both in financial and technical terms.
answer
True
question
Project managers must conduct cash flow analysis to determine net present value.
answer
True
question
Intangible costs can be easily measured in monetary terms.
answer
False
question
When deciding what projects to invest in or continue, one should include sunk costs.
answer
False
question
It is important for project managers to focus on indirect costs because they can be easily controlled.
answer
False
question
If an important supplier goes out of business, management reserves can be set aside to cover the resulting costs.
answer
True
question
Contingency reserves are also known as unknown unknowns.
answer
False
question
A cost management plan can include organizational procedures links, control thresholds, and process descriptions.
answer
True
question
A budgetary estimate is the most accurate of the three types of estimates.
answer
False
question
Budgetary estimates are made even before a project is officially started.
answer
False
question
Definitive estimates are made one year or less prior to project completion.
answer
True
question
Estimates should become more accurate as time progresses.
answer
True
question
Supporting details for an estimate include the ground rules and assumptions used in creating the estimate.
answer
True
question
Analogous estimates are called activity based costing.
answer
False
question
Analogous estimates are the most accurate technique to estimate costs.
answer
False
question
In a bottom up estimate, the size of the individual work items is one of the factors that drives the accuracy of the estimates.
answer
True
question
Parametric models are reliable when the models are flexible in terms of the project's size.
answer
True
question
One of the reasons why project cost estimates are inaccurate is because human beings are biased toward underestimation.
answer
True
question
It is important for project managers to understand that every cost estimate is unique.
answer
True
question
Determining the budget involves allocating the project cost estimate to individual work items over time.
answer
True
question
The project management plan and project funding requirements are inputs of the process of controlling costs.
answer
True
question
The formulas for variances and indexes start with EV, the earned value.
answer
True
question
If cost variance is a positive number, it means that performing the work costs more than planned.
answer
False
question
A negative schedule variance means that it took lesser than planned to perform the work.
answer
False
question
If the cost performance index (CPI) is less than 100 percent, the project is under budget.
answer
False
question
A schedule performance index of one means that the project is on schedule.
answer
True
question
In an earned value chart, when the actual cost line is right on or above the earned value line, it indicates that costs are less than planned.
answer
False
question
Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.
answer
True