question
Intense global competition and rapid technological advances create pressure to develop projects rapidly. This is an example of reducing project duration caused by:
answer
Time to market.
question
Which of the following is NOT considered a project indirect cost?
answer
Equipment.
question
As a project is crashed and project duration is reduced, indirect costs typically:
answer
Decrease.
question
The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.
answer
Crash.
question
An activity's crash cost includes ____ costs.
answer
Direct.
question
When a project manager must reduce project duration but resources are constrained, creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of:
answer
Reducing project scope.
question
One way of reducing project costs is identifying tasks that _________ can do themselves.
answer
Customers.
question
Which of the following is NOT one of the more commonly used options for cutting project costs?
answer
Move the completion date further out.
question
Reducing project duration:
answer
Tends to increase network sensitivity.
question
As a project is crashed and project duration is reduced, direct costs typically:
answer
Increase.