PM test 3

2 May 2024
4.5 (244 reviews)
30 test answers

Unlock all answers in this set

Unlock answers (26)
question
identify the risks
answer
The initial step in the risk management process is to
question
slowly drop
answer
The chances of a risk event occurring as a project proceeds through its life cycle tend to
question
slowly rise
answer
The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
question
risk profile
answer
A list of questions that address traditional areas of uncertainty on a project is termed a
question
assess identified risks
answer
After your team has successfully identified potential risks that could affect the project, what is the next step?
question
risk management
answer
The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as
question
risk breakdown structures
answer
Organizations use __________ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk.
question
Focus on consequences and not on the events that could produce consequences
answer
One common mistake made early in the risk identification process is to
question
risk
answer
An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a
question
risk tracking
answer
Which of the following is NOT one of the steps in the risk management process?
question
people
answer
Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of what type of resource constraint?
question
equipment
answer
A special truck that George needs on his project has been scheduled on another project. This is an example of what type of resource constraint?
question
technical
answer
When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by _________ constraints
question
smoothing
answer
Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resource
question
physical
answer
Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it?
question
resource constrained scheduling
answer
If resources are not adequate to meet peak demands, the resulting reschedule is termed
question
materials
answer
Gene is trying to order the concrete needed to continue his project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint?
question
scope creep
answer
Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?
question
time
answer
When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?
question
information
answer
All of the following are types of resource constraints EXCEPT
question
crash
answer
The shortest possible time an activity can be completed realistically is called ________ time
question
imposed project deadlines
answer
Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year. This may lead to a project that must be done faster than anticipated. This is an example of reducing project duration caused by
question
decrease
answer
As a project is crashed and project duration is reduced, indirect costs typically
question
normal
answer
Before crashing, direct costs for an activity represent normal costs, which typically mean low-cost, efficient methods for completing the activity in a(n) ________ amount of time
question
time to market
answer
Intense global competition and rapid technological advances create pressure to develop projects rapidly. This is an example of reducing project duration caused by
question
incentive contracts
answer
A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion. This is an example of reducing project duration caused by
question
direct and indirect costs
answer
In a Project Cost-Duration Graph, total project costs are a sum of
question
unforeseen project delays
answer
Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an example of reducing project duration caused by
question
increase
answer
As a project is crashed and project duration is reduced, direct costs typically
question
equipment
answer
Which of the following is NOT considered a project indirect cost?