what is a project network?
a. the reporting structure within a project team
b. a group of team members connected through digital communications
c. a graphical representation of the project flow in chart form
d. a representation of activities with horizontal bars showing time to completion and relationship to the project
answer
c
question
what is a horizontal bar chart showing activities /tasks with duration and timing?
answer
Gantt chart
question
Concurrent engineering, which has dramatically reduced the development time for new products, relies on what kind of lag?
Finish to Finish lags
Any of these could be correct
Start to Finish lags
Start to Start lags
Finish to Start lags
answer
d
question
The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called
Hammock activities.
A forward pass.
Concurrent engineering.
Laddering.
Dissecting.
answer
d
question
Arrows on an activity-on-node (AON) project network represent
Dependency.
An activity and dependency.
An activity.
Project flow and dependency.
Project flow.
answer
d
question
Which of the following correctly calculates the early finish for an activity?
LF + DUR
ES + SL
LF + SL
LS + DUR
ES + DUR
answer
e
question
Activities which can take place at the same time are termed
Burst activity.
Parallel activity.
Critical path.
Merge activity.
Independent activity.
answer
b
question
If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a
Multiple start path.
Confused path.
Parallel path.
Critical path.
Dangler path.
answer
e
question
When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
The largest LS of all its immediate successor activities to establish the LF.
The smallest LS of all its immediate successor activities to establish the LF.
The average LS of all its immediate successor activities to establish the LF.
The largest ES of all its immediate successor activities to establish the LF.
The smallest ES of all its immediate successor activities to establish the LF.
answer
b
question
Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of
Having more than one start node.
Looping.
Good network development.
Conditional statements.
Natural network flow.
answer
b
question
If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
Check to see which activities have the most slack
Check to see which activities have the highest risk
Check to see which activities are on the critical path
Check to see which activities cost the least
Check to see which activities have the longest duration
answer
c
question
Which of the following is true about hammock activities?
They are a combination of Start to Start and Start to Finish lags
They are used to identify the use of fixed resources or costs over a segment of a project
They are activities in which the costs are not subject to change
They are an alternative description for the critical path
They are highly sensitive
answer
b
question
The likelihood the original critical path(s) will change once the project is initiated is referred to as
Concurrent engineering.
Sensitivity.
Flexibility.
Resilience.
Rigidity.
answer
b
question
The critical path in a project network is the
Network path with the most difficult activities.
Shortest path through the network.
Longest path through the network.
Network path with the most merge activities.
Network path using the most resources.
answer
c
question
A(n) _________ activity has more than one dependency arrow flowing from it.
Burst
Critical path
Independent
Parallel
Merge
answer
a
question
On a project network, the activity times are derived from the
Work packages.
Project proposal.
Responsibility matrix.
Budget.
Organization breakdown structure.
answer
A
question
System documentation cannot end until three days after testing has started. This is an example of which kind of lag?
Start to Finish
Finish to Start
Finish to Finish
Start to Start
Any of these could be correct
answer
a
question
The minimum amount of time a dependent activity must be delayed to begin or end is referred to as
Cushion.
Laddering.
Lag.
Hammock.
Buffer.
answer
c
question
Which of the following correctly calculates the late start for an activity?
ES - DUR
EF - DUR
LF - SL
ES - SL
LF - DUR
answer
e
question
________ activities must be completed immediately before a particular activity.
Predecessor
Parallel
Successor
Merge
Burst
answer
a
question
The backward pass in project network calculations determines all of the following EXCEPT
Latest time an activity can finish.
The critical path.
How long an activity can be delayed.
Earliest time an activity can finish.
Latest time an activity can begin.
answer
d
question
When translated into a project network, a work package will become
A milestone.
An arrow.
A critical path.
A single activity.
One or more activities.
answer
e
question
Which of the following will correctly calculate the total slack in an activity?
Either LS - ES or LF - EF
LF - ES
LF - EF
LS - LF
LS - ES
answer
a
question
Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of
Free Slack.
Functional Slack.
Total Slack.
Critical Slack.
Shared Slack.
Start to Start
answer
c
question
The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?
Any of these could be correct
Start to Finish
Finish to Finish
Finish to Start
Start to Start
answer
d
question
________ activities are to be completed immediately following a particular activity.
Burst
Predecessor
Parallel
Merge
Successor
answer
e
question
Which of the following can be used without coordinating with managers of succeeding activities?
Float pad
Total slack
Free slack
Slip pad
Critical float
answer
c
question
The amount of time an activity can be delayed and yet not delay the project is termed
Free slack.
Float pad.
Slip pad.
Critical float.
Total slack.
answer
e
question
Which of the following represents an activity on an activity-on-node (AON) project network?
An arrow
Both an arrow and a line
A line
An arrow, a line and a node all represent activities
A node
answer
e
question
Information to develop a project network is collected from the
Work breakdown structure.
Budget.
Organization breakdown structure.
Project proposal.
Responsibility matrix.
answer
a
question
Which of the following is provided by both the project network and the work breakdown structure?
Sequencing
Activity duration
Dependencies
Interrelationships
Timing
answer
b
question
The forward pass in project network calculations determines all of the following EXCEPT
The critical path.
Duration of the project.
Earliest time an activity can begin.
Earliest time an activity can finish.
How soon the project can finish.
answer
a
question
If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?
Finish to Finish
Start to Finish
Start to Start
Any of these could be correct
Finish to Start
answer
a
question
Which of the following is NOT one of the basic rules to follow when developing project networks?
Conditional statements are allowed but looping statements are not allowed
Each activity must have a unique identification number
An activity cannot begin until all preceding activities have been completed
Networks flow from left to right
An activity identification number must be larger than that of any preceding activities
answer
a
question
A sequence of connected, dependent activities is termed a(n)
Activity chain.
Parallel path.
Path.
Path of events.
Dependent chain.
answer
c
Haven't found what you need?
Search for quizzes and test answers now
Quizzes.studymoose.com uses cookies. By continuing you agree to our cookie policy