question
Information to develop a project network is collected from the A. Organization breakdown structure B. Work breakdown structure C. Budget D. Project proposal E. Responsibility matrix
answer
Work breakdown structure
question
Which of the following represents an activity on an AON project network? A. An arrow B. A line C. A node D. Both A and B are correct E. A, B, and C are all correct
answer
A node
question
Arrows on an AON project network represent: A. An activity B. Project flow C. Dependency D. Both B and C are correct E. Both A and B are correct
answer
Both B and C are correct
question
When translated into a project network, a work package will become A. A single activity B. One or more activities C. A milestone D. A critical path E. An arrow
answer
One or more activities
question
Which of the following is provided by a project network but not by the work breakdown structure? A. Dependencies B. Sequencing C. Timing D. Both A and B are correct E. A, B, and C are all correct
answer
A, B, and C are all correct
question
On a project network, the activity times are derived from the A. Organization breakdown structure B. Work packages C. Budget D. Project proposal E. Responsibility matrix
answer
Work packages
question
Part of a project is to Develop Product Specifications. This is best classified as a(n) A. Event B. Path C. Activity D. Node E. Milestone
answer
Activity
question
An activity that has more than one dependency arrow flowing into it is termed a(n) A. Parallel activity B. Critical path C. Burst activity D. Merge activity E. Independent activity
answer
Merge activity
question
The critical path in a project network is the A. Shortest path through the network B. Longest path through the network C. Network path with the most difficult activities D. Network path using the most resources E. Network path with the most merge activities
answer
Longest path through the network
question
A/an _________ activity has more than one dependency arrow flowing from it. A. Parallel B. Critical path C. Burst D. Merge E. Independent
answer
Burst
question
An item on a project network is Design Software Completed. This is best described as a(n) A. Event B. Path C. Activity D. Node E. Milestone
answer
Event
question
Activities which can take place at the same time are termed A. Parallel activity B. Critical path C. Burst activity D. Merge activity E. Independent activity
answer
Parallel activity
question
A sequence of connected, dependent activities is termed a(n) A. Critical path B. Parallel path C. Activity chain D. Path E. Dependent chain
answer
Path
question
An AON project network uses which of the following basic building blocks? A. Arrows B. Bars C. Nodes D. Both A and C are correct E. A, B, and C are all correct
answer
Both A and C are correct
question
Which of the following is not one of the basic rules to follow when developing project networks? A. An activity cannot begin until all preceding activities have been completed B. Each activity must have a unique identification number C. Conditional statements are allowed but looping statements are not allowed D. An activity identification number must be larger that that of any preceding activities E. Networks flow from left to right
answer
Conditional statements are allowed but looping statements are not allowed
question
________ activities must be completed immediately before a particular activity. A. Merge B. Burst C. Predecessor D. Successor E. Critical
answer
Predecessor
question
________ activities are to be completed immediately following a particular activity. A. Merge B. Burst C. Predecessor D. Successor E. Critical
answer
Successor
question
The forward pass in project network calculations determines the A. Earliest time's activities can begin B. Earliest time's activities can be finished C. Duration of the project D. Both A and B are correct E. A, B, and C are all correct
answer
A, B, and C are all correct
question
The backward pass in project network calculations determines the A. Latest time's activities can begin B. Earliest time's activities can be finished C. Critical path D. Both A and C are correct E. A, B, and C are all correct
answer
Both A and C are correct
question
Which of the following correctly calculates the early finish for an activity? A. LS + DUR B. ES + DUR C. LF +DUR D. ES + SL E. LF + SL
answer
ES + DUR
question
Which of the following correctly calculates the late start for an activity? A. EF - DUR B. ES - DUR C. LF - DUR D. ES - SL E. LF - SLACK
answer
LF - DUR
question
The amount of time an activity can be delayed and yet not delay the project is termed A. Total slack B. Free slack C. Critical float D. Float pad E. Slip pad
answer
Total slack
question
Which of the following will correctly calculate the total slack in an activity? A. LS - ES B. LF - EF C. LS - LF D. LF - ES E. Both A and B are correct
answer
Both A and B are correct
question
The laying pipe example in the text illustrates the concept of A. Laddering B. Hammock activities C. Critical path D. Concurrent engineering E. Forward pass
answer
Laddering
question
Using a special color copy machine for a tradeshow publication illustrates the concept of A. Laddering B. Hammock activities C. Critical path D. Concurrent engineering E. Forward pass
answer
Hammock activities
question
If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first? A. Check to see which activities cost the least B. Check to see which activities have the longest duration C. Check to see which activities are on the critical path D. Check to see which activities have the most slack E. Check to see which activities have the highest risk
answer
Check to see which activities are on the critical path
question
Typically an activity on a project network represents A. A single work package B. One or more tasks from a work package C. Several work packages D. A sub-deliverable E. A cost account
answer
One or more tasks from a work package
question
Project network logic errors include which of the following? A. Activities with less than 1 day duration B. Sequences such as "if test successful build prototype, if failure redesign" C. A sequence such as B succeeds A, C succeeds B, A succeeds C D. Both B and C are network logic errors E. A, B, and C are all network logic errors
answer
Both B and C are network logic errors
question
Which company utilized concurrent engineering to design a new line of cars and in the process completed its development six months ahead of schedule? A. General Motors B. Chrysler C. Ford D. Nissan E. Toyota
answer
Chrysler
question
The minimum amount of time a dependent activity must be delayed to begin or end is referred to as: A. Hammock B. Laddering C. Lag D. Cushion E. Buffer
answer
Lag
question
The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag? A. Start to Start B. Start to Finish C. Finish to Finish D. Finish to Start E. Any of these could be correct
answer
Finish to Start
question
Concurrent engineering is a good example of good use of A. Start to Start lags B. Start to Finish lags C. Finish to Finish lags D. Finish to Start lags E. Any of these could be correct
answer
Start to Start lags
question
If testing cannot be completed any earlier than four days after the prototype is built, which of the following type of lag exists? A. Start to Start B. Start to Finish C. Finish to Finish D. Finish to Start E. Any of these could be correct
answer
Finish to Finish
question
Which of the following represents an activity on an AOA project network? A. An arrow B. A line C. A node D. Both A and B are correct E. A, B, and C are all correct
answer
A line
question
Nodes on an AOA project network represent: A. An activity B. An event C. Responsibility D. Both B and C are correct E. Both A and B are correct
answer
An event
question
Activity
answer
Task(s) of the project that consumes time while people/equipment either work or wait.
question
Activity-on-arrow (AOA)
answer
Activity-on-arrow method for drawing project networks. The activity is shown as an arrow.
question
Activity-on-node (AON)
answer
Activity-on-node method for drawing project networks. The activity is on the node (rectangle).
question
Burst activity
answer
An activity that has more than one activity immediately following it.
question
Concurrent engineering
answer
Crossfunctional teamwork in new-product development projects that provides product design, quality engineering, and manufacturing process engineering all at the same time.
question
Critical path
answer
The longest activity path(s) through the network. The critical path can be distinguished by identifying the collection of activities that all have the same minimum slack.
question
Gantt chart
answer
A graphic presentation of project activities depicted as a time-scaled bar line.
question
Hammock activity
answer
A special-purpose, aggregate activity that identifies the use of fixed resources or costs over a segment of the project—e.g., a consultant. Derives its duration from the time span between other activities.
question
Lag relationship
answer
The relationship between the start and/ or finish of a project activity and the start and/or finish of another activity. The most common lag relationships are (1) finish-to-start, (2) finish-to-finish, (3) start-tostart, and (4) start-to-finish.
question
Merge activity
answer
An activity that has more than one activity immediately preceding it.
question
Parallel activity
answer
One or more activities that can be carried on concurrently or simultaneously.
question
Sensitivity
answer
The likelihood that the critical path(s) will change once the project begins to be implemented.