question
Scheduling refers to specifying:
answer
The start and completion times of jobs.
question
Triage by nurses in an emergency room would be an example of:
answer
Sequencing.
question
Staff scheduling needs all of the following except:
answer
Flow time estimates.
question
Which of the following is not a consideration when designing an appointment system?
answer
Determining the appropriate sequencing rule
question
The time needed to process a given set of jobs is called:
answer
Makespan.
question
The numerical difference between the completion time and the due date is called:
answer
Lateness
question
Scheduleanywhere.com an online software helps clients do all the following except:
answer
Decide how much to overbook for each day of the week.
question
The shortest processing time (spt) rule:
answer
Minimizes work-in-process inventory
question
The sequencing rule that minimizes the maximum number of jobs that are past due from a given set of jobs is:
answer
Earliest due date (edd).
question
If the highest priority is to minimize the average job lateness then the job sequence should begin with those jobs requiring:
answer
The shortest processing time.
question
In a two-resource sequencing problem:
answer
The goal is to minimize makespan.
question
A requirement of johnson's two-resource sequencing rule is:
answer
Jobs must be processed through each work center in the same job sequence.
question
Johnson's sequencing rule is used to sequence:
answer
Several jobs through two work centers.
question
Which of the following is not a criterion for evaluating job-sequencing rules?
answer
Sum of processing times
question
The chief disadvantage of the shortest processing time (spt) rule is:
answer
Long-duration jobs may have excessive completion times.
question
Gantt charts can be used to:
answer
Display the two-resource sequencing solution using johnson's rule.
question
Which of the following is an example of a situation for which a gantt chart would be appropriate?
answer
Monitoring job schedules