question
The most difficult and unappreciated process in project management is often
answer
Planning
question
The project cost management knowledge area maps to the __________ process group through the activities of estimating costs and budget determination.
answer
planning
question
Developing a _______ is a planning process that occurs in the Project Integration Management knowledge area.
answer
project management plan
question
The improvement of the product and process in the Scrum Method is discussed at the _______.
answer
sprint reflection meeting
question
________ processes include defining and authorizing a project or project phase.
answer
Initiating.
question
The _____ process involves gaining stakeholder and customer acceptance of the final products and services and bringing the project, or project phase, to an orderly end.
answer
closing
question
Examples of _____ processes include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements.
answer
executing
question
Which of the following is a planning process associated with project scope management?
answer
Collecting requirements
question
_____ is a planning process that is within the Project Scope Management knowledge area.
answer
Creation of a WBS
question
Which of the following is a pre-initiation task?
answer
Developing a business case for a project
question
Organizational process assets update is the output of the closing process of
answer
project integration management
question
The main purpose of project plans is to
answer
guide project execution.
question
Which of the following is true about the agile method?
answer
It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product.
question
________ is an iterative software development process that focuses on team productivity and delivers software best practices to all team members.
answer
Rational Unified Process
question
The project scope management knowledge area maps to the ________ process group through the activities of scope validation and scope control.
answer
monitoring and controlling
question
Which of the following activities is a part of the planning process of the Scrum?
answer
Creating product backlogs, sprint backlogs and release backlogs are all part of the planning process of the scrum.
question
A _____ is usually not necessary to the Scrum method.
answer
team contract