Project Management Quiz 8 (CH7)

17 April 2023
5 (49 reviews)
70 test answers

Unlock all answers in this set

Unlock answers (66)
question
They can be easily measured.
answer
Which statement is true of tangible costs? Answers: a. They are difficult to quantify. b. They cannot be calculated in monetary terms. c. They can be easily measured. d. Their examples include goodwill and prestige.
question
earned value
answer
Variances are calculated by subtracting the actual cost from which value? Answers: a. schedule variance b. rate of performance c. planned value d. earned value
question
True
answer
IT project managers must be able to present and discuss project information both in financial and technical terms. Answers: True False
question
False
answer
The primary output of the planning cost management process is a change request. Answers: True False
question
False
answer
Analogous estimates are called activity-based costing. Answers: True False
question
False
answer
A budgetary estimate is the most accurate of the three types of estimates. Answers: True False
question
True
answer
A cost management plan can include organizational procedures links, control thresholds, and process descriptions. Answers: True False
question
True
answer
Budgetary estimates are made even before a project is officially started. Answers: True False
question
They allow for future situations that can be partially planned for.
answer
Which statement is true of contingency reserves? Answers: a. They are also known as unknown unknowns. b. They allow for future situations that can be partially planned for. c. They allow for dollar amounts to be used to cover existing, fixed costs. d. They are not included in a cost baseline.
question
revenues minus expenditures
answer
How are profits best defined? Answers: a. revenues plus expenses b. expenses plus net income c. costs plus revenues d. revenues minus expenditures
question
direct
answer
Newtech Inc. hires John for the position of a software programmer to work on their new project. Salary paid to John by Newtech Inc. would be an example of which type of costs? Answers: a. indirect b. direct c. intangible d. sunk
question
cost budgeting
answer
Which process results in a cost baseline as a main output?
question
bottom-up
answer
What type of estimate is a cost estimation tool that involves estimating individual work items or activities and summing them to get a project total? Answers: a. budgetary b. bottom-up c. analogous d. parametric
question
cost forecasts
answer
Which is an output of the process of controlling costs? Answers: a. project funding requirements b. cost forecasts c. basis of estimates d. scope baselines
question
True
answer
The formulas for variances and indexes start with EV, the earned value. Answers: True False
question
False
answer
Analogous estimates are the most accurate technique to estimate costs. Answers: True False
question
determining the budget
answer
Which process involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance? Answers: a. determining the budget b. controlling costs c. finalizing policies for project costs d. estimating costs
question
It provides an estimate of what a project will cost.
answer
Which statement is true of a order of magnitude estimate? Answers:a. Its timeframe is always less than a year prior to project completion. b. It is used to allocate money into an organization's budget. c. It is a type of estimate that is done in the final stages of a project. d. It provides an estimate of what a project will cost.
question
False
answer
In an earned value chart, when the actual cost line is right on or above the earned value line, it indicates that costs are less than planned. Answers: True False
question
cost control
answer
Work performance information and cost forecasts are main outputs of which process? Answers: a. cost estimating b. cost budgeting c. cost pricing d. cost control
question
life cycle costing
answer
Which process helps develop an accurate projection of a project's financial expenses and benefits? Answers: a. life cycle costing b. fast tracking c. crashing d. critical path analysis
question
budgetary
answer
What type of estimate is a cost estimation tool used to allocate money into an organization's budget? Answers: a. definitive b. rough order of magnitude c. budgetary d. ballpark
question
False
answer
A negative schedule variance means that it took less time than planned to perform the work. Answers: True False
question
False
answer
It is important for project managers to focus on indirect costs because they can be easily controlled. Answers: True False
question
project cost management
answer
What type of management includes the processes required to ensure that a project team completes a project within an approved budget? Answers: a. project quality management b. project cost management c. project scope management d. project time management
question
estimating costs
answer
Which process involves developing an approximation of the costs of resources needed to complete a project? Answers: a. estimating costs b. controlling costs c. determining the budget d. finalising the cost baseline
question
plan how costs will be managed
answer
What is the first step in project cost management? Answers :a. allocate project cost estimates to individual material resources b. control project costs and monitor cost performance c. plan how costs will be managed d. develop several estimates of costs for different types of resources
question
definitive
answer
What type of estimate is used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs? Answers: a. budgetary b. final c. definitive d. rough order of magnitude
question
parametric
answer
Which type of estimating uses project characteristics in a mathematical model to estimate project costs?
question
managing changes to the project budget
answer
What does the process of controlling costs primarily involve? Answers: a. finalising the procedures for project costs b. determining a basis for estimates c. managing changes to the project budget d. determining the policies for project costs
question
True
answer
Definitive estimates are made one year or less prior to project completion. Answers: True False
question
earned value minus the actual cost
answer
Which statement best defines cost variance? Answers: a. planned value minus the rate of performance b. rate of performance minus earned value c. earned value minus the actual cost d. planned value plus actual costs
question
cost budgeting
answer
The main goal of which process is to produce a cost baseline for measuring project performance and project funding requirements? Answers: a. cost estimating b. cost planning c. cost controlling d. cost budgeting
question
True
answer
Supporting details for an estimate include the ground rules and assumptions used in creating the estimate. Answers: True False
question
not directly related to the products or services of a project.
answer
Which statement is true regarding indirect costs? Answers: a. those that can be easily controlled by managers. b. those that cannot be allocated to projects. c. not directly related to the products or services of a project. d. directly related to performing the project.
question
work performance data
answer
Which is an input of the process of controlling costs? Answers: a. change requests b. scope baseline c. work performance data d. cost forecasts
question
True
answer
Parametric models are reliable when the models are flexible in terms of the project's size. Answers: True False
question
True
answer
It is important for project managers to understand that every cost estimate is unique. Answers: True False
question
False
answer
Contingency reserves are also known as unknown unknowns. Answers: True False
question
False
answer
When deciding what projects to invest in or continue, one should include sunk costs. Answers: True False
question
Selected Answer:True
answer
Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control. Answers: True False
question
True
answer
Determining the budget involves allocating the project cost estimate to individual work items over time. Answers: True False
question
True
answer
A schedule performance index of one means that the project is on schedule. Answers: True False
question
It can be used to estimate the projected time to complete the project
answer
Which is true of the schedule performance index (SPI)? Answers: a. It is the ratio of planned value to actual costs. b. It can be used to estimate the projected time to complete the project. c. It means that a project is behind schedule if an SPI is greater than one. d. It means that a project is ahead of schedule if SPI is lesser than one or hundred percent.
question
True
answer
One of the reasons why project cost estimates are inaccurate is because human beings are biased toward underestimation. Answers: True False
question
True
answer
In a bottom-up estimate, the size of the individual work items is one of the factors that drives the accuracy of the estimates. Answers: True False
question
Management reserves
answer
Which reserves allow for future situations that are unpredictable? Answers: a. Known unknowns b. Management reserves c. Contingency reserves d. Cost baseline reserves
question
They are time-intensive and expensive to develop.
answer
Which statement is true of bottom-up estimates? Answers: a. They are time-intensive and expensive to develop. b. They are also known as parametric estimating. c. They are based on the actual cost of a previous, similar project. d. They are most accurate when they involve large, extensive work items.
question
False
answer
Intangible costs can be easily measured in monetary terms. Answers: True False
question
People lack estimating experience.
answer
Which is most likely to be a reason for inaccuracies in information technology cost estimates? Answers: a. Estimates take a long time to be worked out. b. Only software development provides the scope for estimates to be accurate. c. People lack estimating experience. d. Human beings are biased toward overestimation.
question
False
answer
If the cost performance index (CPI) is less than 100 percent, the project is under budget. Answers: True False
question
analogous estimates
answer
Which type of estimate uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project? Answers: a. definitive estimates b. bottom-up estimates c. analogous estimates d. parametric estimates
question
Intangible costs
answer
Which costs are difficult to measure in monetary terms? Answers: a. Fixed costs b. Direct costs c. Tangible costs d. Intangible costs
question
It is an estimate of the value of the physical work actually completed.
answer
Which is true of earned value? Answers: a. It is also known as the planned value. b. It is based solely on the total cost estimate to be spent on an activity. c. It is an estimate of the value of the physical work actually completed. d. It is the actual cost plus the planned cost.
question
True
answer
If an important supplier goes out of business, management reserves can be set aside to cover the resulting costs. Answers: True False
question
True
answer
Project managers must conduct cash flow analysis to determine net present value. Answers: True False
question
planned value
answer
What is another term used for budget? Answers: a. earned value b. actual cost c. indirect cost d. planned value
question
Cash flow analysis
answer
Which method is used for determining the estimated annual costs and benefits for a project? Selected Answers: a. Cash flow analysis b. Requirements analysis c. Critical path analysis d. Present value analysis
question
estimate the projected cost of completing the project
answer
What is the purpose of a cost performance index (CPI)? Answers: a. indicate that the planned and actual costs are equal if CPI is more than one b. indicate that a project is under budget if CPI is less than one c. estimate the ratio of earned value to planned value d. estimate the projected cost of completing the project
question
True
answer
Estimates should become more accurate as time progresses. Answers: True False
question
definitive
answer
Which type of estimate should be used if the cost estimate for a project is used a basis for contract awards and performance reporting? Answers: a. definitive b. budgetary c. analogous d. rough order of magnitude
question
Electricity used to run its factories
answer
Soles is a footwear company which has recently set up its store in Ambrosia. To manufacture its products, Soles incurs a range of different costs. Which would be an example of an indirect cost? Answers: a. Salary paid to factory workers b. Electricity used to run its factories c. Cost of machines to produce shoes d. Cost of leather used to manufacture shoes
question
earned value minus the planned value
answer
Which statement best defines schedule variance? Selected Answers: a. earned value minus the actual cost b. planned value plus the rate of performance c. planned value plus the earned value d. earned value minus the planned value
question
sunk
answer
Good Earth, a company manufacturing packaged food products, sets up its stores in Baltonia. However, a year later, the company closes the store down due to high operating costs. In such a scenario, the money spent in paying for the rent of the store in Baltonia would be an example of which costs? Answers: a. sunk b. intangible c. recurring d. direct
question
They are most reliable when previous projects are similar in fact with current projects.
answer
Which statement is true of analogous estimates? Answers: a. They are most reliable when previous projects are similar in fact with current projects. b. Their main disadvantage is that they cost more than other techniques. c. They use project characteristics in a mathematical model to estimate project costs. d. They are the only technique which do not require expert judgement.
question
False
answer
Overrun is the additional percentage amount by which estimates exceed actual costs. Answers: True False
question
ballpark
answer
What is a rough order of magnitude estimate also referred to as? Answers: a. definitive b. budgetary c. ballpark d. final
question
False
answer
If cost variance is a positive number, it means that performing the work costs more than planned. Answers: True False
question
top-down
answer
What term is used for analogous estimates? Answers: a. top-down b. bottom-up c. parametric d. budgetary
question
True
answer
The project management plan and project funding requirements are inputs of the process of controlling costs. Answers: True False