ISDS 3115 Ch. 14

2 April 2024
4.4 (103 reviews)
14 test answers

Unlock all answers in this set

Unlock answers (10)
question
Which of the following statements is NOT true about EOQ?
answer
The EOQ is preferable when dependent demand exists.
question
What is the act of breaking up an order and running part of it ahead of schedule?
answer
lot splitting
question
Which of the following lot-sizing techniques is likely to prove the most complex to use?
answer
Wagner-Whitin
question
Which of the following statements is NOT true about DRP?
answer
The DRP procedure starts with the forecast at the supplier level.
question
The gross material requirements plan combines
answer
a master production schedule and the time-phased schedule
question
Which of the following statements about DRP is NOT true?
answer
DRP pushes inventory through the system
question
Which of the following pieces of information is NOT contained in a bill of material?
answer
lead times
question
What sends a lot to two different machines for the same operation?
answer
operations splitting
question
Which of the following statements is NOT true?
answer
For any product, some components of that product are independent demand items.
question
Which of the following is NOT true about MRP limitations?
answer
MRP does not tell you that a job needs to be completed on a certain week or day.
question
Which of the following is an advantage of ERP?
answer
It creates commonality of databases.
question
Supply chain management systems in the grocery industry that tie sales to buying, to inventory, to logistics, and to production are called
answer
efficient consumer response
question
The operations manager has two important tools available to deal with MRP system nervousness. Those tools are
answer
time fences and pegging
question
Which of the following statements is NOT true about MRP?
answer
MRP is an independent demand technique used in a production environment.