MISY 4350 Ch. 6

23 January 2023
4.7 (244 reviews)
40 test answers

Unlock all answers in this set

Unlock answers (36)
question
The first process involved in project time management is _____ .
answer
planning schedule management
question
Which of the following processes in project time management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?
answer
Defining activities
question
In project time management, which of the following processes generate the main outputs of an activity list, activity attributes, and a milestone list?
answer
Defining activities
question
In project time management, which of the following processes primarily involve identifying and documenting the relationships between project activities?
answer
Sequencing activities
question
In project time management, which of the following processes involve calculating the number of work periods that are needed to complete individual activities?
answer
Estimating activity durations
question
In project time management, which of the following processes involve analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?
answer
Developing the schedule
question
In project time management, the process of_____ primarily involves checking and managing changes to the project schedule.
answer
controlling the schedule
question
In project time management, a(n) _____ is an output of controlling the schedule
answer
project management plan update
question
Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?
answer
Project charter
question
Which of the following is a difference between an activity list and an activity attribute?
answer
An activity attribute provides more schedule-related information about each activity than an activity list.
question
A(n) _____ on a project is a significant event that normally has no duration.
answer
milestone
question
In project time management, the main goal of _____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.
answer
defining activities
question
In project time management, the next step after defining project activities is:
answer
determining their dependencies.
question
Which of the following types of dependencies are inherent in the nature of work being performed on a project?
answer
Mandatory
question
_____ dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.
answer
Discretionary
question
Which of the following dependencies involve relationships between project and non-project activities?
answer
External
question
In an AOA network diagram, _____ occur when two or more activities follow a single node.
answer
bursts
question
A network diagramming technique in which boxes represent activities is known as a(n) _____.
answer
PDM
question
AOA network diagrams use only _____ dependencies.
answer
finish-to-start
question
Which of the following is a relationship in which the "from" activity cannot start until the "to" activity is started?
answer
Start-to-start
question
Which of the following is true of a finsih-to-finish dependency?
answer
It is a dependency in which the "from" activity must be finished before the "to" activity can be finished.
question
Which of the following is true of dummy activities?
answer
They show logical relationships between activities.
question
Which of the following is one of the main outputs of estimating activity resources process?
answer
Project documents update
question
After working with key stakeholders to define activities and calculate their resources, the next process in project time management is to:
answer
estimate the duration of activities.
question
In project time management, the ultimate goal of _____ is to provide a basis for monitoring project progress for the time dimension of the project.
answer
developing a schedule
question
_____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.
answer
Gantt charts
question
Which of the following is a network diagramming technique used primarily to predict total project duration?
answer
Critical path analysis
question
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.
answer
longest; shortest
question
The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____.
answer
free slack
question
_____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.
answer
Total slack
question
The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.
answer
late start date
question
The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____.
answer
crashing
question
Which of the following techniques involve doing activities in parallel that one would normally do in sequence?
answer
Fast tracking
question
A similarity between the crashing technique and the fast tracking technique is that:
answer
both can shorten the time needed to finish a project.
question
Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
answer
feeding buffers
question
_____ states that work expands to fill the time allowed.
answer
Parkinson's Law
question
A difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) is that:
answer
PERT uses different duration estimates whereas CPM uses one specific duration estimate.
question
Which of the following is a similarity between scope control and schedule control?
answer
Both are portions of the integrated change control process under project integration management.
question
Which of the following is an output of schedule control?
answer
Lessons-learned reports
question
A draft schedule for a project is most likely to be found in a _____.
answer
project charter