ISDS 3115 Chapter 3

25 July 2022
4.7 (114 reviews)
23 test answers

Unlock all answers in this set

Unlock answers (19)
question
The three phases involved in the management of large projects are:
answer
planning, scheduling and controlling.
question
Which of the following does NOT belong to the planning phase of projection management?
answer
Monitoring resources
question
The project organization may be less helpful when:
answer
the job is familiar to the existing organization
question
Which of the following is the THIRD level in work breakdown structure (WBS)
answer
Subtasks in major tasks
question
Gantt charts are
answer
planning charts used to schedule resources and allocate time.
question
Which of the following is NOT part of project controlling?
answer
sequencing and allotting time to all project activities.
question
The critical path of a network is the:
answer
longest time path through the network
question
How is the EF computed?
answer
ES + Activity time
question
Which of these time estimates is NOT used in PERT?
answer
Standard time
question
What is the shortest duration required to complete an activity?
answer
crash time
question
Which of the following is a limitation of PERT and CPM
answer
There is the inherent danger of placing too much emphasis on the critical path
question
Among the following, critical path and slack time analysis MOST help
answer
pinpoint activities that need to be closely watched
question
What is the most popular example of specialized software for managing projects?
answer
microsoft project
question
Which of the following is not a technique that allows managers to plan, schedule, and control, projects?
answer
factor - rating method
question
Which of the following activities are NOT part of project scheduling?
answer
Make sure all necessary activities are finished in the proper sequence and on time.
question
Which of the following is an advanatage of PERT and CPM?
answer
Straightforward concept and not mathematically complex
question
The most realistic estimate of the time required to complete an activity as referred to as?
answer
most likely tim
question
Computerized PERT/CPM reports and charts do NOT include
answer
probability estimate for on time completion
question
Which column in microsoft project defines the precidence relationships among the activites?
answer
predecessors
question
Which of the following is a direct responsibility of the project manager?
answer
making sure that the people assigned to the project receieve the motivation, direction, and information needed to do their job.
question
Which of the following is not used for computation in CPM?
answer
normal time
question
The latest finish of an activity is:
answer
min (LS of all immediate following activities)
question
Which of the following is not true about gantt charts?
answer
cant charts adequately illustrate the interrelationships between the activites and resources